Sawyer Says South Mills Development Could ‘Outrun’ Sewer Plant as Moratorium Nears End

South Mills wastewater averaged about 25% of stated capacity in July, while Camden says proposed development will require substantially more treatment capacity.

Sawyer Says South Mills Development Could ‘Outrun’ Sewer Plant as Moratorium Nears End
Camden Tribune | Courtesy Camden BOC Sept. 8 2026

CAMDEN, N.C. — Camden County Public Works Manager Charles “Chas” Sawyer told commissioners Sept. 8 that development in South Mills could “outrun the sewer plant,” even though July wastewater flow averaged 25,079 gallons per day against the plant's stated 100,000-gallon-per-day capacity.

Sawyer said the N.C. Department of Environmental Quality wanted updated South Mills development information to refine future wastewater-flow projections. The county's current Capital Improvement Plan provides the context: it says additional treatment and disposal capacity is needed for residential developments already proposed and estimates about $9 million to add another 100,000 gallons per day. The plan says that expansion would cover the first two building phases before officials determine how much more capacity is required.

Current flow, however, is not the same as future demand. Camden has not publicly presented a development-by-development accounting showing how much existing capacity is already committed, to which projects, and how much remains available.

The issue predates the current moratorium.

A 2012 development-capacity report, citing the county's 2010 Water and Sewer Master Plan, said 48,000 gallons per day of the plant's capacity had already been committed to existing or developing residential and business projects. The report concluded that available wastewater capacity was essentially “already spoken for.”

An April 2012 Comprehensive Plan steering-committee document called for Camden to “Establish Formal Policies for Evaluating Utility Allocation” because water and wastewater capacity was finite. A March 2012 presentation projected about 60,000 gallons per day of wastewater demand after the South Mills sewer extension, leaving roughly 40,000 gallons per day for future development. It also identified about 270 South Mills-area homes needing sewer because of failing septic systems, with projected demand of another 73,000 gallons per day.

By June 2020, the county was describing a different picture. During review of South Mills Landing, a Planning Board packet said approximately 90,000 gallons of wastewater capacity was available and that the county was evaluating expansion of the treatment plant. The same packet said, “South Mills water is at capacity.”

Four years later, commissioners imposed the current 30-month development moratorium, citing water and wastewater limitations. It is scheduled to expire Dec. 25, 2026.

Sawyer's Sept. 8 report also showed drinking water operating near its stated limit: July production averaged about 681,500 gallons per day against 720,000 gallons per day of stated capacity, or roughly 95%.

As of Aug. 26, DEQ said it was still waiting for the completed wastewater model and had no permit application under review for the proposed discharge. On Sept. 8, Sawyer said updated development information was still being incorporated into the projections.

On Aug. 5, Sawyer was sent questions about pending approvals, plant capacity, DEQ review, water-production figures, and the county's plans if approvals or construction were not completed before the moratorium expired. County Manager Erin Burke, Board Chairman Jason Banks, and county staff were copied. Sawyer did not respond.

The unresolved public-record question is specific: how much South Mills wastewater capacity is already committed to development in the pipeline, and how much will remain when the moratorium ends?