Chowan County data center moratorium goes to public hearing Monday

Chowan County commissioners hold a public hearing Monday at 5:30 p.m. on a draft ordinance that would pause new approvals for data centers and cryptocurrency mining in unincorporated areas until November 2027.

Chowan County data center moratorium goes to public hearing Monday
Illustration: Chowan County weighs a one-year pause on data center approvals. Camden Tribune/Camden Graphics.

EDENTON, N.C. — Chowan County commissioners will decide Monday whether to stop taking new applications for data centers and cryptocurrency mining operations for a year. A public hearing on the proposed Chowan County data center moratorium opens the board's 5:30 p.m. special meeting, and commissioners could vote the same night.

The meeting is at the Chowan County Public Safety Center, 305 W. Freemason St. The moratorium is the only business item on the agenda.

The draft ordinance says the board "has observed recent interest, requests and potential applications" for these facilities in unincorporated Chowan. It does not name a company, a site or a project.

What the pause would cover

As drafted, the county would not accept, process or approve special use permits, conditional zoning, rezonings, building permits or other development approvals for a data center, cryptocurrency mining facility or "other high-impact data processing facility." The draft does not define that last term.

The pause would not stop every project. State law protects projects with a valid building permit, special use permit applications already accepted as complete, approved site-specific vesting plans, projects with substantial good-faith spending on a prior approval, and subdivision plats accepted before the hearing was called.

Where it applies

The county's draft covers unincorporated Chowan only. Edenton already has its own pause.

The Edenton Town Council voted unanimously Nov. 10 to adopt a 60-day moratorium on certain data center approvals, the Albemarle Observer reported. The town's pause runs through Jan. 10, 2027.

How long it would last

The county pause would run from Nov. 23, 2026, through Nov. 23, 2027, unless commissioners end or change it sooner.

Extending it would be harder. Under state law, the county could extend the pause only if it has taken the reasonable steps promised in its plan and new facts and conditions justify more time.

Why the county wants the time

The draft lists five concerns: heavy electricity demand on existing utility lines, noise from cooling systems and backup generators, large water use for cooling, hazardous materials and electronic waste, and conflicts with rural and agricultural zoning.

The board considered handling proposals through its existing special use permit process, the ordinance states. It rejected that route because current rules lack noise limits, utility capacity requirements and setbacks written for these facilities.

The 12-month plan

The ordinance sets a schedule for writing permanent rules:

  • Months 1-4: Study energy, water, noise and land-use impacts with local utility providers and the UNC School of Government.
  • Months 4-6: Draft zoning amendments covering allowed districts, setbacks, noise limits and utility capacity conditions.
  • Months 6-10: Hold public workshops and Planning Board meetings on the draft rules.
  • Months 10-12: The Planning Board sends a recommendation, and commissioners hold hearings on final rules.

Neighbors have acted

Camden County commissioners adopted a five-month data center moratorium Aug. 3, the Camden Tribune reported. It runs through Jan. 3, 2027, or ends sooner if the county adopts zoning amendments covering those uses.

Gates County has posted a draft ordinance with the same title and one-year structure as Chowan's. The posted copy is unsigned.

Currituck County commissioners held an information-only work session on data centers in July. County officials said then that no data center had been proposed there.

Statewide, at least 25 county-level jurisdictions and 40 municipal entries had adopted or extended some form of data center pause or restriction by mid-November, the North State Journal reported.

How to weigh in

Residents can speak during Monday's public hearing. The agenda and draft ordinance are posted on the county's meeting page.

The Camden Tribune will report the outcome of Monday's vote.