Latest development
Camden Tribune reported Aug. 26 that DEQ was still waiting for the completed wastewater model and had no permit application under review.
Timeline
- — Camden Tribune reported that developers sued Camden County over the moratorium and permit reversals.
- — County minutes showed the approximately 600-signature claim cited during the moratorium debate had not been checked for duplicates.
- — The Tribune reported the 387-unit proposal was headed to an Aug. 31 appeal hearing.
- — DEQ said it was still waiting for the wastewater model as the moratorium neared its scheduled end.
Key officials and agencies
- Camden County Board of Commissioners
- Camden County Board of Adjustment
- Camden County Planning and Building
- N.C. Department of Environmental Quality
Important numbers
- 30-month moratorium
- 387 proposed residential units